Abstract. This project introduces the problem of scheduling jobs across geo-distributed data cen-ters. It includes the introduction, background and challenges of this problem. Finally, it lists all the requirements and rules for each group. Please read this document carefully and complete the corresponding tasks.
Keywords: Geo-distributed Data Center Networks, Graph Algorithm, Scheduling.
• Data Analytic Job Scheduling Problem
It has now become commonly accepted that the volume of data |from end users, sensors, and algorithms |has been growing exponentially, and mostly stored in geographically distributed data centers around the world. Big data processing refers to applications that apply machine learning algorithms alike to process such large volumes of data, typically supported by modern data-parallel frameworks such as MapReduce and Spark. Big data processing has become a routine in governments and multinational corporations, especially those in the business of social media and Internet advertising.
A data analytic job typically proceeds in several computation stages where there are precedence constraints among them. Each stage may consist of a number of computation tasks that are executed in parallel. For example, there are only one stage for both job A and job B in Figure 1, and each stage contains two parallel tasks. To start a new computation stage, intermediate data from the preceding stage needs to be obtained, which may initiate multiple network ows.
Fig. 1. An example of scheduling multiple jobs across Fig. 2. A possible assignment of jobs for the problem
geo-distributed data centers, retrieved from [1]. in Figure 1, retrieved from [1].
Figure 1 shows an example of scheduling multiple jobs across geo-distributed data centers. For job A, both of its tasks, tA1 and tA2, require 100 MB of data from input dataset A1 stored in DC1 (Data Center 1), and 200 MB of data from A2 located at DC3. For job B, the amounts of data to be read by task tB1 from dataset B1 in DC2 and B2 in DC3 are both 200 MB; while task tB2 needs to read 200 MB of data from B1 and 300 MB from B2. These tasks are to be assigned to available computing slots in the
Page 1 of 5
CS214-Algorithm@SJTU Group Project Instructors: Xiaofeng Gao & Lei Wang
three data centers, each with two slots, two slots, and one slot, respectively. The amounts of available bandwidth of inter-datacenter links are illustrated in the gure, with the unit of MB/s. The bandwidth of inner-datacenter links, though not shown in the gure, is 1000 MB/s. The goal is to nd a placement of data, intermediate results and computation tasks so that the average completion time of two jobs is minimized.
Figure 2 gives a feasible solution of the problem. The job completion time is determined by the network transfer time and execution time of each task. For simplicity, we assume that all tasks take 1 second to execute. For the assignment of job A, task tA2 is assigned to the only available computing slot in DC3, and tA1 is placed in DC2, which result in a network transfer time of maxf100=80; 200=160; 100=150g = 1:25 seconds. For the assignment of job B, DC1 and DC2 are selected to distribute task tB1 and tB2, respectively, resulting in the transfer time of maxf200=80; 200=100; 300=160g = 2:5 seconds. The average completion time is thus (2:25 + 3:5)=2 = 2:875 seconds.
Traditionally, we transfer all the data that are geographically distributed to be processed to a single data center, so that they can be processed in a centralized fashion. However, this wisdom becomes prac-tically unfeasible nowadays. First, it may not be practical to move user data across country boundaries, due to legal reasons or privacy concerns. Second, the cost, in terms of both bandwidth and time, to move large volumes of data across geo-distributed data centers may become prohibitive as the volume of data grows exponentially.
A better design may be to move computation tasks to where the data is, so that data can be processed locally within the same data center. Of course, the intermediate results after such processing may still need to be transferred across data centers. In this case, designing the best possible task assignment strategy to assign tasks to data centers is important, since di erent strategies lead to di erent ow patterns across data centers, and ultimately, di erent job completion times.
Your team is assigned to design an algorithm to tackle this challenge. To do so, you will have to consider many questions. How hard is it to nd an optimal scheduling algorithm? How to determine the data and job placement across geo-distributed data centers? How to balance fairness in terms of resource allocation and e ciency when scheduling multiple jobs? Please keep theses questions in mind and accomplish the detailed tasks in Section 2.
• Single Job Scheduling
Before we tackle the multi-job scheduling problem, let us rst learn some wisdom from the algorithms for single-job scheduling. We introduce the DAG scheduling model as follows.
A data analytic job, which is essentially a parallel program, can be represented by a directed acyclic graph (DAG) G = (V; E), where V is a set of v nodes and E is a set of e directed edges. A node in the DAG represents a task of the job. The weight of a node vi is called the computation cost and is denoted by wi. The edges in the DAG, each of which is denoted by (vi; vj), correspond to the communication messages and precedence constraints among the nodes. The weight of an edge is called the communication cost of the edge and is denoted by c(vi; vj). To make it clear, assume there is another task tA3 in job A in the problem introduced in Figure 1, and tA3 needs 100 MB from intermediate result of tA1. If we place tA3 in the empty slot of DC1 in Figure 2, then c(vtA1; vtA3) would be 100/80 = 1.25 seconds. The source node of an edge is called the parent node while the sink node is called the child node. A node with no parent is called an entry node and a node with no child is called an exit node.
The precedence constraints of a DAG dictate that a node cannot start execution before it gathers all of the messages from its parent nodes. The communication cost between two tasks assigned to the same processor (i.e. abstracted to be computation slots in Figure 1 and 2, we now use the term processor and slot interchangeably) is assumed to be zero. If node vi is scheduled to some processor, then ST (vi) and F T (vi) denote the start-time and nish-time of vi, respectively. After all the nodes have been scheduled, the schedule length is de ned as maxifF T (vi)g across all processors. The goal of scheduling is to minimize maxifF T (vi)g. Note that this goal of min-max is di erent from the previous one.
Page 2 of 5
CS214-Algorithm@SJTU Group Project Instructors: Xiaofeng Gao & Lei Wang
Fig. 3. An example of a data analytic job consisting of multiple stages.
Figure 3 shows a data analytic job whose precedence constraints are more complicated than the previous one. It has in all 7 tasks and 5 stages. Most importantly, only when an old stage is nished may a new stage start to be computed.
In DAG scheduling, it is assumed that the processors do not share memory and communication relies solely on message-passing. Note that di erent processors in the same data center can also raise commu-nication cost, since the inner bandwidth is large yet not in nity. For simplicity, suppose all processors to be homogeneous, having the same speed and processing capability. The processors are connected by an interconnection network with a certain topology. The topology may be fully connected or of a particular structure such as a hypercube or mesh. Figure 1 is essentially a fully connected network for the processors.
• Task and Requirements
3.1 Task: Multi-Job Scheduling with Max-Min Fairness
Consider you are scheduling multiple jobs with limited computing slots in each data center. In this case, di erent jobs may be competing for resources. We want the resource to be allocated fairly. To quantify fairness, there is a notion called max-min fairness [5,8].
Max-Min Fairness Consider a network composed of a set V of nodes, a set E of links with given capacities Ce (e 2 E), and a set D of connections (demands). Each connection d (d 2 D) is assigned a prede ned path Pd between its end nodes; each such path is identi ed with the set of links it traverses, i.e., Pd E, d 2 D. Now let xd denote the bandwidth allocated to path Pd and x = (xd : d 2 D) 2 RjDj be the corresponding allocation vector. We are interested in nding a feasible allocation vector x 2 X (the set of all feasible allocation vectors will be denoted by X) which is fair.
Clearly, vector x is feasible if x 0 and
X
xd Ce; e 2 E;
d2D:e2Pd
which is called the capacity constraint; it assures that for any link e its load does not exceed its capacity. We say that an allocation vector x0 is said to be max-min fair in X if x0 2 X and x0 ful lls the following property:
For any allocation vector x 2 X and for any connection d such that xd > x0d there exists a connection d0 such that xd0 < x0d0 x0d.
To get more intuition of the de nition, let us look at a simple example. Three persons want to share 100cl of beer in three glasses of di erent volumes, respectively 25, 40, and 50cl. Obviously the most fair sharing given the volumes of glasses would be the one given in the Figure 4. All people get the amount
Page 3 of 5
CS214-Algorithm@SJTU Group Project Instructors: Xiaofeng Gao & Lei Wang
Fig. 4. Example of fair beer sharing between three persons.
not exceeded than required, and for those whose demand is not satis ed, the allocation among them is fair.
Now back to the scheduling problem. The goal is to minimize the average completion time of all jobs while maintaining max-min fairness on computation resource. Please accomplish following tasks:
1. Formalize the multi-job scheduling problem with notations. Especially, formalize the max-min fair-ness on computation resource in this problem.
2. How hard is this problem? Is it in P, or NP, or NP-Complete?
3. Please design an algorithm for this problem and analyze its complexity.
4. Test you algorithm on the attached toy data. Visualize your result to illustrate your design of algorithm if possible.
5. Test the e ciency of your design by simulations. You can collect data from open-source websites or generate data based on your understanding of the problem. If you collect data, please state where you nd it and explain why it is suitable for testing. If you generate data, please brie y explain how you generated data based on your assumptions.
• Report Requirements
You need to submit a report for this project, with the following requirements:
1. Your report should have the title, the author names, IDs, email addresses, the page header, the page numbers, gure for your simulations, tables for discussions and comparisons, with the corresponding gure titles and table titles.
2. Your report is English only, with a clear structure, divided by sections, and may contain organiza-tional architecture like itemizations, de nitions, or theorems and proofs.
3. Please include reference section and acknowledgment section. You may also include your feelings, suggestion, and comments in the acknowledgment section.
4. Please de ne your variables clearly. If needed, a symbol table is strongly recommended to help readers catch your design.
5. Please also include your latex source and simulation codes upon submission.
Acknowledgment
This problem is motivated by Prof. Bo Li (bli@cse.ust.hk) from Department of Computer Science and Engineering at The Hong Kong University of Science and Technology, designed by Prof. Xiaofeng Gao (gao-xf@cs.sjtu.edu.cn) from Department of Computer Science and Engineering at Shanghai Jiao Tong University. Tianyao Shi from CS2016@SJTU (sthowling@sjtu.edu.cn) scribed and nalized the project. Yihao Xie from JI2016@SJTU(crystalys@sjtu.edu.cn) and Haolin Zhou from SPEIT@SJTU (kozilelo@sjtu.edu.cn) helped on literature review. Runbo Ni from SPEIT@SJTU (pqross@sjtu. edu.cn) provided many suggestions.
Page 4 of 5
CS214-Algorithm@SJTU Group Project Instructors: Xiaofeng Gao & Lei Wang
References
1. Li Chen, Shuhao Liu, Baochun Li, and Bo Li, Scheduling Jobs across Geo-Distributed Datacenters with Max-Min Fairness, IEEE Transactions on Network Science and Engineering (TNSE), 6(3):488-500, 2019.
2. Chen Chen, Wei Wang, and Bo Li, Performance-Aware Fair Scheduling: Exploiting Demand Elasticity of Data Analytics Jobs, IEEE International Conference on Computer Communications (INFOCOM), 504-512, 2018.
3. Yu-Kwong Kwok and Ishfaq Ahmad, Static Scheduling Algorithms for Allocating Directed Task Graphs to Multiprocessors, ACM Computing Surveys, 31(4):406{471, 1999.
4. Je rey Dean and Sanjay Ghemawat, MapReduce: Simpli ed Data Processing on Large Clusters, Communica-tions of the ACM (CACM), 51(1):107{113, 2008.
5. Dritan Nace and Michal Pioro, Max-Min Fairness and its Applications to Routing and Load-Balancing in Communication Networks: A Tutorial, IEEE Communications Surveys and Tutorials, 10(1-4): 5-17, 2008.
6. Zhiming Hu, Baochun Li, and Jun Luo, Flutter: Scheduling Tasks Closer to Data across Geo-Distributed Datacenters, IEEE International Conference on Computer Communications (INFOCOM), 1-9, 2016.
7. Qifan Pu, Ganesh Ananthanarayanan, Peter Bodik, Srikanth Kandula, Aditya Akella, Paramvir Bahl, and Ion Stoica, Low Latency Geo-distributed Data Analytics, ACM Conference on Applications, Technologies, Architectures, and Protocols for Computer Communication (SIGCOMM), 421{434, 2015.
8. Ali Ghodsi, Matei Zaharia, Benjamin Hindman, Andy Konwinski, Scott Shenker, and Ion Stoica, Dominant Resource Fairness: Fair Allocation of Multiple Resource Types, USENIX Symposium on Networked Systems Design and Implementation (NSDI), 1-14, 2011.