Each project partner should turn in their joint code to each of their handin directories. Each person also needs to specify a partners.txt file. (Thu 10/17)
A user program that includes "pstat.h" must not have to also include "proc.h" (or other miscellaneous .h files) to compile correctly. To avoid the problem where procstat is not defined, you can either have pstat.h itself include proc.h, or you can move the definition of enum procstate from proc.h to pstat.h. Depending on your approach, you may need to modify which header files are included where. You may also want to use include guards in your .h files. See piazza for more info about include guards. https://piazza.com/class/jyivrc1wvcv7dh?cid=7 (https://piazza.com/class/jyivrc1wvcv7dh?cid=7) Our test programs will not compile correctly if you do not adhere to this requirement. (Thu 10/17)
Make sure the very first process that is added to a queue is added to the tail, thus immediately incrementing the value of qtail to 1. (Thu 10/17)
Why might getpinfo() fail (and return -1)? If the pointer passed in as a parameter does not point to valid, allocated memory. (Thu 10/17)
This project may be performed with one project partner. We recommend that each of you understand each portion of your code. This project does not entail writing too many lines of code, but it does require that you get everything exactly right. Thus, if you both work together on understanding the existing code and debugging your new code, you will probably work most efficiently.
This project is technically due at 5:00 pm, but, if you are able to connect to the handin directory, you may turn in your project up through midnight that day.
Objectives
To understand existing code for performing context-switches in the xv6 kernel
To implement a basic multi-level round-robin scheduler where priorities are statically assigned To implement a system call that extracts process states
To implement a user-level process that controls the scheduling of children processes
Overview
In this project, you’ll be implementing a multi-level queue scheduler in xv6. This multi-level queue scheduler is easier to implement than the multi-level feedback queue (MLFQ) we discussed in lecture because your scheduler is missing the word "feedback"; that is, the priorities in your scheduler are
https://canvas.wisc.edu/courses/154998/assignments/664429 1/8
5/15/2020 P4: xv6 Scheduling
changed not based on the dynamic behavior of processes, but are based on explicit system calls to modify the priority of each process.
The basic idea is simple. Build an MLQ scheduler with four priority queues; the top queue (numbered 3) has the highest priority and the bottom queue (numbered 0) has the lowest priority. When a process uses up its time-slice (counted as a number of ticks), it stays at its priority level, but is moved to the back of that queue. The scheduling method in each of these queues is thus Round Robin (RR). The time-slices for higher priorities will be shorter than lower priorities.
To make your life easier and our testing easier, you should run xv6 on only a ** single CPU ** . Make sure in your Makefile CPUS := 1 .
Particularly useful for this project: Chapter 5 (https://pdos.csail.mit.edu/6.828/2018/xv6/book-rev11.pdf) in xv6 book.
Background
Before implementing anything, you should first have an understanding of how the scheduler works in xv6.
Most of the code for the scheduler is localized and can be found in proc.c. The header file proc.h describes the fields of an important structure, each of the proc structures in the global ptable.
You should first look at the routine scheduler() which is essentially looping forever. After it grabs an exclusive lock over ptable, it then ensures that each of the RUNNABLE processes in the ptable is scheduled for a timer tick. Thus, the scheduler is implementing a simple Round Robin (RR) policy. For example, if there are three processes A, B and C, then the pattern under the vanilla round-robin scheduler will be A B C A B C … , where each letter represents a process scheduled within a timer tick.
A timer tick is about 10ms, and this timer tick is equivalent to a single iteration of the for loop over the ptable in the scheduler() code. Why 10ms? This is based on the timer interrupt frequency setup in xv6 and you may find relevant code for incrementing the value of ticks in trap.c.
When does the current scheduler make a scheduling decision? Basically, whenever a thread calls sched(). You'll see that sched() switches between the current context back to the context for scheduler(); the actual context switching code for swtch() is written in assembly and you can ignore those details. So, when does a thread call sched() ? You'll find three places: when a process exits, when a process sleeps, and during yield().
When a process exits and when a process sleeps are intuitive, but when is yield() called? You'll want to look at trap.c to see how the timer interrupt is handled and control is given to scheduling code; you may or may not want to change the code in trap().
Other important routines that you may need to modify include allocproc() and userinit(). Of course, you may modify other routines as well.
https://canvas.wisc.edu/courses/154998/assignments/664429 2/8
5/15/2020 P4: xv6 Scheduling
MLQ Requirements
Your MLQ scheduler must follow these very precise rules:
Four priority levels, numbered from 3 (highest) down to 0 (lowest).
The time-slice associated with priority 3 is 8 timer ticks; for priority 2 it is 12 timer ticks; for priority 1 it is 16 timer ticks, and for priority 0 it is 20 timer ticks.
There are three events which may cause a new process to be scheduled: whenever the xv6 10 ms timer tick occurs, when a process exits, or when a process sleeps. At each of those three points, the highest priority process must be run.
You should not trigger a new scheduling event when a new process arrives, wakes, or has its priority modified through setpri(); you should wait until a timer tick to schedule the highest priority process. If there are more than one processes on the same priority level, then you should schedule all the processes at that particular level in a Round Robin fashion. After a process consumes its time-slice it should be moved to the back of its queue. For example, if a process is at the highest priority level, which has a time-slice of 8 timer ticks, then you should schedule this process for 8 ticks before moving to the next process.
When a timer tick occurs, whichever process was currently using the CPU should be considered to have used up an entire timer tick's worth of CPU, even if it did not start at the previous tick. (Note that a timer tick is different than the time-slice.)
When a new process arrives, it should inherit the priority of its parent process. The first user process should start at the highest priority.
Whenever a process wakes or moves to a new priority, it should always be added to the back of that queue with a full new time slice.
You will not implement any mechanism for starvation; if a process is never at the highest priority, it will never run.
New system calls
You’ll need to create several new system calls for this project.
The first is int setpri(int PID, int pri). This sets the priority of the specified PID to pri. You should check that both PID and pri are valid; if they are not, return -1. When the priority of a process is set, the process should go to the end of the queue at that level and should be given a new time-slice of the correct length. The priority of a process could be increased, decreased, or not changed (in other words, even when the priority of a process is set to its current priority, that process should still be moved to the end of its queue and given a new timeslice). Note that calling setpri() may cause a new process to have the highest priority in the system and thus need to be scheduled when the next timer tick occurs. (When testing your pinfo() statistics below, we will not examine how you account for the case when setpri() is applied to the calling process.)
The second is int getpri(int PID). This returns the current priority of the specified PID. If the PID is not valid, it returns -1.
https://canvas.wisc.edu/courses/154998/assignments/664429 3/8
5/15/2020 P4: xv6 Scheduling
The third is int fork2(int pri). This routine is exactly like the existing fork() system call, except the newly created process should begin at the specified priority. Thus, fork() could now be implemented as fork2(getpri()) since by default the child process inherits the priority of the parent process. If pri is not a valid priority, fork2() should return -1.
The last is int getpinfo(struct pstat *). Because your MLQ implementation is all in the kernel level, you need to extract useful information for each process by creating this system call so as to better test whether your implementation works as expected.
To be more specific, this system call returns 0 on success and -1 on failure. If success, some basic information about each process: its process ID, how many timer ticks have elapsed while running in each level, which queue it is currently placed on (3, 2, 1, or 0), and its current procstate (e.g., SLEEPING, RUNNABLE, or RUNNING) will be filled in the pstat structure as defined
struct pstat {
int inuse[NPROC]; // whether this slot of the process table is in use (1 or 0)
int pid[NPROC]; // PID of each process
int priority[NPROC]; // current priority level of each process (0-3)
enum procstate state[NPROC]; // current state (e.g., SLEEPING or RUNNABLE) of each process
int ticks[NPROC][4]; // total num ticks each process has accumulated at each priority
int qtail[NPROC][4]; // total num times moved to tail of queue (e.g., setprio, end of timeslice, w
aking)
};
Most of the fields should be self explanatory. To be precise, ticks is the total number of timer ticks each process has acquired at each of the 4 priority levels; that is, ticks should be incremented exactly once for one process when a timer tick occurs.
The qtail field should be incremented whenever a process is moved to the back of its queue. Remember, a process is moved to the back of its queue whenever it finishes it time-slice, wakes, or has its priority set by setpri(). Important: This field should be incremented even if there is only one process at a priority level (e.g., a process A finishes its time-slice and it is moved to the tail of its queue; however, there is no other process at that priority so A is scheduled again; the value of qtail for A would still be incremented).
You can decide if you want to update your pstat statistics whenever a change occurs, or if you have an equivalent copy of these statistics in ptable and want to copy out information from the ptable when getpinfo() is called.
The file should be copied from ~cs537-1/projects/scheduler/pstat.h Do not change the names of the fields in pstat.h .
User-Level Scheduling
https://canvas.wisc.edu/courses/154998/assignments/664429 4/8
5/15/2020 P4: xv6 Scheduling
To demonstrate that your scheduler is doing at least some of the right things, you will implement a toy user-level scheduler, userRR. The idea of a user-level scheduler is that a regular user-level process (probably running at high priority) controls exactly which of its children processes is scheduled by explicitly setting the priority of the chosen process to a higher level than the other processes.
Your implementation of userRR has the following arguments:
userRR <user-level-timeslice> <iterations> <job> <jobcount>
User-level-timeslice is the number of timer ticks (in 10ms intervals) that should be given to each of the child processes. Iterations is the number of times each job should be run. Job is the name of the job that userRR should start; you can assume that each job is identical and will run forever. JobCount is is the number of copies of job that should be started.
How to implement round-robin at user level? Probably start the userRR process at the highest priority. Begin by having the parent process fork2() and exec() each of the jobcount copies of job at a low priority. Then, pick one of the processes to schedule and set it to some other priority; go to sleep for the user-level timeslice; when the parent wakes, it is time to schedule a different process. When it is done with the specified number of iterations, userRR should kill all the child processes, call getpinfo, and print all the structures out.
To have jobs for userRR to run, you will also need to implement a second user-level program, loop. The job loop should not take any arguments and should just forever sleep for 10 ticks and then print out its
pid.
For example, if the program is run as:
userRR 5 3 loop 2
Two instances of loop will be started; let's assume they are assigned pid 12 and 13. Pid 12 will be run for 5 ticks, followed by pid 13 for 5 ticks; then a second iteration with pid 12 for 5 more ticks and pid 13 for 5 ticks; finally, the 3rd iteration with pid 12 for 5 ticks and pid 13 for 5 ticks.
We will not test your implementation of userRR extensively; the purpose of userRR is primarily for you to test your implementation of your MLQ scheduler.
Tips
We recommend writing very small amounts of code and testing each change you make (e.g., by running forktest) rather than implementing too much functionality at one time.
Most of the code for the scheduler is quite localized and can be found in proc.c; the associated header file, proc.h is also quite useful to examine (and modify). You will also want to look at trap.c to see how the timer interrupt is handled and control is given to scheduling code; you may or may not want to
https://canvas.wisc.edu/courses/154998/assignments/664429 5/8
5/15/2020 P4: xv6 Scheduling
change the code in trap(). To change the scheduler, not too much needs to be done; study its control flow and then try some small changes.
As part of the information that you track for each process, you will probably want to know its current priority level and the number of timer ticks it has left. Somewhere you might also want to track if an event occurred that should trigger a scheduling event on the next timer tick.
It is much easier to deal with fixed-sized arrays in xv6 than allocating kernel memory. For simplicity, we recommend that you use statically-allocated memory to represent each priority queue (though you will need to move jobs within and across priority queues). Of course, your fixed-sized array may contain pointers to other structures if you find this useful; or, your statically-sized array could include pointers to act as a linked-list.
You’ll need to understand how to fill in the structure pstat in the kernel and pass the results to user space and how to pass the arguments from user space to the kernel. Good examples of how to pass arguments into the kernel are found in existing system calls. In particular, follow the path of read() , which will lead you to sys_read() , which will show you how to use int argint(int n, int
*ip) in syscall.c (and related calls) to obtain a pointer that has been passed into the kernel.
Now to implement MLQ, you need to schedule the process for some time-slice, which is some multiple of timer ticks.
If learn better by listening to someone talk while they walk through code, you are welcome to watch this (old) video of another CS 537 instructor talk about how the default xv6 scheduler works. Note that the project for that semester is different than what you are implementing, but you might find the code walk through useful.
https://www.youtube.com/watch?v=eYfeOT1QYmg&feature=youtu.be
(https://www.youtube.com/watch?v=eYfeOT1QYmg&feature=youtu.be)
(https://www.youtube.com/watch?v=eYfeOT1QYmg&feature=youtu.be)
Code
We suggest that you start from the initial source code of xv6 at ~cs537-1/projects instead of your own code from p2 as bugs may propagate and affect this project.
Begin by copying this file ~cs537-1/projects/xv6-rev10.tar.gz and gunzip and untar it. Also, copy pstat.h.
https://canvas.wisc.edu/courses/154998/assignments/664429 6/8
5/15/2020 P4: xv6 Scheduling
To run the xv6 environment, use make qemu-nox. Doing so avoids the use of X windows and is generally fast and easy. However, quitting is not so easy; to quit, you have to know the shortcuts provided by the machine emulator, qemu. Type control-a followed by x to exit the emulation. There are a few other commands like this available; to see them, type control-a followed by an h.
When debugging, remember that gdb can be quite useful!
When working with a project partner, you may want to be able to read and write the files in a shared directory on the instructional machines. The CSL machines run a distributed file system called AFS that allows you to give different file permissions to your project partner than to everyone else.
First, use the "fs" command to make sure no one can snoop about your directories. Let's say you have a directory where you are working on project 2, called "~remzi/p2". To make sure no one else can look around in there, do the following:
'cd' into the directory
prompt> cd ~remzi/p2
check the current permissions for the "." directory ("." is the current dir)
prompt> fs la .
make sure system:anyuser (that is, anybody at all) doesn't have any permissions
prompt> fs sa . system:anyuser ""
check to make sure it all worked
prompt> fs la .
Access list for . is
Normal rights:
system:administrators rlidwka
remzi rlidwka
As you can see from the output of the last "fs la ." command, only the system administrators and remzi can do anything within that directory. You can give your partner rights within the directory by using "fs sa" again:
prompt> fs sa . dusseau rlidwka
prompt> fs la .
Access list for . is
Normal rights:
system:administrators rlidwka
remzi rlidwka
dusseau rlidwka
https://canvas.wisc.edu/courses/154998/assignments/664429 7/8
5/15/2020 P4: xv6 Scheduling
If at any point you see the directory has permissions like this:
prompt> fs la .
Access list for . is
Normal rights:
system:administrators rlidwka
remzi rlidwka
system:anyuser rl
that means that any user in the system can read ("r") and list files ("l") in that directory, which is probably not what you want.
Testing
We recommend making sure that your scheduler can handle a large range of jobs. If you can run usertests and forktests, your scheduler is probably fairly robust (though unfortunately it might not be implementing the correct policy). We recommend next using your implementation of userRR to see if it has the expected behavior.
More information will be made available here later.
Handin
Each project partner should turn in their joint code to each of their handin directories.
So that we can tell who worked together on this project, each person should place a file named partners.txt in their handin/p4 directory. The format of partners.txt should be exactly as follows:
cslogin1 wisclogin1 Lastname1 Firstname1
cslogin2 wisclogin2 Lastname2 Firstname2
It does not matter who is 1 and who is 2. If you worked alone, your partners.txt file should have only one line. There should be no spaces within your first or last name; just use spaces to separate fields.
To repeat, both project partners should turn in their code and both should have this partners.txt file in their handin/p4 directory.
https://canvas.wisc.edu/courses/154998/assignments/664429 8/8